Recuproces Investment BV
Plant 5
Recuproces Investment BV
- New construction of facility
- Location: Meer, Belgium
- By 2024 operational
- 5 MWe
Electricity off-take |
11.5 MWe |
Heat off-take |
14.5 MW |
Feedstock |
Agricultural waste |
Planning Permission |
Permits granted, unlimited (industrial zoning): Binergy Meer; Permit: GPBV-code: BE.VL.000002123.INSTALLATION Installatiefiche/BE.VL.000002123.INSTALLATION |
Grid connection |
36 kV – starting Aug 2023 |
Site |
John Lijsenstraat, 2321 Hoogstraten, Zoning: Industrial (nijverheid) |
Commission |
Starting August 2023 |
Technical Facility Data
PRODUCT |
Mass (tons/day) |
Mass into (tons/year) |
% Share Nutrition |
Biomass – Solid |
258 |
94.000 |
34% |
Biomass – Liquid |
0 |
0 |
0% |
Manure – Solid |
0 |
0 |
0% |
Manure – Liquid |
107 |
39.000 |
14% |
Internal Return (Thin Fraction) |
385 |
|
51% |
Total Fermenter Input |
749 |
133.000 |
100% |
Required Digestion Volume and Digesters
Digester diameter |
26,0 |
m |
Liquid height |
7,0 |
m |
Number of digestors |
6,0 |
# |
Digester content |
22.298 |
m³ |
Dwell time |
30 |
days |
Organic load |
8,49 |
kg OS/m³/day |
Site Parameters
– Electric power 24/7 |
11,5 |
MWe |
– Biomass (annualized) |
133.000 |
ton |
– Organic Mineral Grains (annualized) |
29.166 |
ton |
– Gross margin (annualized) |
18.608.827 |
EUR |
– Range “Green Power” for families |
23.174 |
familie |